Kitchen Extension Progress 3

Stage 9 : Wiring, Fitting, Piping....




Kitchen Extension Progress 2



Stage 6 : Tampal simen dinding (Plastering)




















Stage 7 : Roof Beam


Stage 8 : Pasang atap genting & Ceiling luar,.... (Roof Installation & Fitting Window n Door Frame)



Kitchen Extension Progress 1

Stage 3 : Ikat besi (Strengthening the structure)


 Stage 4 : Curah simen cara mudah (Cementing process)














Tunggu kering....

















Stage 5 : Batu blok tiba... (Unloading the bricks)



Kitchen Extension Project

Date Started : 02/03/2013
Cost : RM10 500.00 ++
Project : Kitchen Extension + Simple Table Top

Stage 1 : Pecah batu (Demolition)




Stage 2 : Piling (10 batang tiang batu)